Client City of Escondido
Date of completion August, 2016
Project designer Michael Baker International
- Construction Cost: $7,834,044.68
PROJECT BACKGROUND: Install approximately 13,780 lineal feet of 24-inch diameter DIP recycled water main pipeline, and 13,800 linear feet of 15-inch diameter SDR35 brine pipeline, asphalt concrete (AC) pavement, steel casing pipes, concrete manholes, recycled water isolation valves, blowoffs, air/vac’s, connections to existing facilities, protection of existing facilities, surface restoration, and other pipeline appurtenances and related work.